![]() Friday, May 09, 2008 Time:10:05:11 AMEST |
|||||||||
|
|
![]() Spring Run clean-up in Carey has been hampered by the wet weather but the work was progressing last week. Cleaning and maintaining the run is only a small part of plans to fight future flood waters. Photo by Mike Lang. Carey's share of new school estimated at $11.9 million Final cost estimates for Carey's new school are in and according to Paul Brown, project manager for Resource International's pre-construction services, Carey's portion of the $27.8 million project would be $11.9 million (43%) while the state would pick up the remaining $15.9 million (57%). ODOT preparing time schedule for downtown A schedule for Carey's downtown renovation project is being prepared this week, says Lori A. Brinkman, consultant contract manager with District 1 of the Ohio Department of Transportation. Construction of Carey's new emergency services building is on hold – at least for now. Work on the $876,000 structure that began on March 4 ran into a major snag recently when the concrete that was poured for the building developed a rash of "blemishes and spider-web cracking."
|
![]() ![]()
|
|||||||
![]() 1198 E. Findlay Street Carey, Ohio 43316 (419) 396-7567 Fax: (419) 396-7527
| |||||||||